=PS1 Documention=
=PS1 Documentation=
An PS1 is an enginnering document that's required for all Moddex Product for New Zealand. There are PS1's avaialable to view on the NZ One Drive, or in some cases a specific PS1 is made for an project.
An PS1 is an engineering document that's required for all Moddex Product for New Zealand. There are PS1's available to view on the NZ One Drive, or in some cases a specific PS1 is made for an project.


Should you require a PS1 for a project, it will be mentioned in the original handover
Should you require a PS1 for a project, it will be mentioned in the original handover
==Standard PS1 documentation==
<div class="toccolours mw-collapsible mw-collapsed">
===Assistrail===
<div class="toccolours mw-collapsible">
[[File:PS1-AR-1.png|frameless|1000px]]
[[File:PS1-AR-2.png|frameless|1000px]]
</div>
===Tuffrail===
<div class="toccolours mw-collapsible">
[[File:PS1-TR-1.png|frameless|1000px]]
[[File:PS1-TR-2.png|frameless|1000px]]
</div>
===Conectabal===
<div class="toccolours mw-collapsible">
[[File:PS1-CB-1.png|frameless|1000px]]
[[File:PS1-CB-2.png|frameless|1000px]]
[[File:PS1-CB-3.png|frameless|1000px]]
[[File:PS1-CB-4.png|frameless|1000px]]
</div>
===Bikesafe===
<div class="toccolours mw-collapsible">
[[File:PS1-BS-1.png|frameless|1000px]]
[[File:PS1-BS-2.png|frameless|1000px]]
[[File:PS1-BS-3.png|frameless|1000px]]
</div>
===Kliptread===
<div class="toccolours mw-collapsible">
[[File:PS1-KT-1.png|frameless|1000px]]
</div>
</div>
=MOE Type Work Design Intent/Shop Drawings SOP=
Please ensure the following points are reviewed & adhered to when reviewing MOE Type Shop drawings designs, anything not inline with these SOP’s please have Drafting team revise prior sending DI for client approval.
*4 hole baseplates by default unless told otherwise
*No Chemical Anchors-only use HDG 12mm screw bolt for concrete fixings
*75mm concrete edge distance will always be achievable onsite unless specifically stated meaning we can use Concrete screws unless reduced edge distance(50mm) is required
*Stainless Steel 180mm Coach screws in all timber areas with SS washer & Nylon separation washer
*All “handrails” and top rails to be 32nb
*Some situations where any standalone 1100mm high barriers are (Ie. Between canopy poles) could be 40nb top rail
*No closure bend/stop starts on parallel deck rails, always ensure end to end in one complete run wherever practical
*No handrails (AR150) to be attached to building cladding unless this is explicitly shown on plans/marked up drawings, AR10 (Stanchion mounted handrail) is the minimum requirement
=Green Rule=
For at least on end of the pipe, the sum of the tail and bend length (X+Y) must be at least 300mm, otherwise add 200mm green. Any tail (X) must be a minimum of 80mm, otherwise add 200mm green.
[[File:NZGREEN.png|200px]]

Latest revision as of 22:33, 10 December 2025

PS1 Documentation[edit]

An PS1 is an engineering document that's required for all Moddex Product for New Zealand. There are PS1's available to view on the NZ One Drive, or in some cases a specific PS1 is made for an project.

Should you require a PS1 for a project, it will be mentioned in the original handover

Standard PS1 documentation[edit]

Assistrail[edit]

Tuffrail[edit]

Conectabal[edit]

Bikesafe[edit]

Kliptread[edit]

MOE Type Work Design Intent/Shop Drawings SOP[edit]

Please ensure the following points are reviewed & adhered to when reviewing MOE Type Shop drawings designs, anything not inline with these SOP’s please have Drafting team revise prior sending DI for client approval.

  • 4 hole baseplates by default unless told otherwise
  • No Chemical Anchors-only use HDG 12mm screw bolt for concrete fixings
  • 75mm concrete edge distance will always be achievable onsite unless specifically stated meaning we can use Concrete screws unless reduced edge distance(50mm) is required
  • Stainless Steel 180mm Coach screws in all timber areas with SS washer & Nylon separation washer
  • All “handrails” and top rails to be 32nb
  • Some situations where any standalone 1100mm high barriers are (Ie. Between canopy poles) could be 40nb top rail
  • No closure bend/stop starts on parallel deck rails, always ensure end to end in one complete run wherever practical
  • No handrails (AR150) to be attached to building cladding unless this is explicitly shown on plans/marked up drawings, AR10 (Stanchion mounted handrail) is the minimum requirement

Green Rule[edit]